01. Strakonicka grade-separated intersection
A connection of motorways D1, D5 and R4 was completed by realization of the
construction segments 512, 513 and 514, which are part of the south and southeast
segments of Prague´s Bypass. Technical difficulty is illustrated by the longest bridge in the Czech
Republic. The 2km long bridge was designed by a subsidiary company Novak&Partner s.r.o.
Other demanding structures that are part of this route are 1.7km long Lochkov tunel and
grade-seperated intersection Strakonicka, for which the conceptual traffic solution
was completely reworked.
| Designer: | Valbek, spol. s r.o., branch Liberec, Novák & partner, spol. s.r.o. - subsidiary company |
|---|---|
| Owner: | Ředitelství silnic a dálnic Praha |
| Contractor: | Sdružení STRABAG-HOCHTIEF-BÖGL |
| Start of construction: | 2006 |
| End of construction: | 2010 |